Cambridge Park Drive Area Drainage Improvements and Stormwater Wetland Project

Drainge improvements and wetland construction in the Cambridgepark Drive area.


This project has been completed. No further updates to this project page will be made.

October 30, 2013

The construction activities for the stormwater outfall and stormwater wetland are substantially complete.  A grand opening ceremony was help on October 15, 2013 to celebrate the opening to the public of the new Stormwater Constructed Wetland and recreational features.  Please refer to the "Documents" and "Photo" tabs for more information. 

---------------------------------------------------------------------------------------------------------------------

August 22, 2013

The Contractor on Contract 12 will finish final paving of the Fitchburg Cutoff Bike Path that runs parallel to the Alewife Reservation Wetland project, once this is completed the contractor will close (August 23rd) the Cambridge Park Drive access road to the bike path. Hence bicyclists traveling from Belmont to Alewife will have to enter the path at Brighton St. (Belmont) and at Alewife T-Station Access Road (Alewife). Click here to view sketch.

---------------------------------------------------------------------------------------------------------------------

August 19, 2013

This week, crews working on the guard rails, bicycle path, and the treatment of invasive plants.

---------------------------------------------------------------------------------------------------------------------------------------------------

June 11, 2013

The city’s contractor will continue to focus on surface restoration.

Surface restoration of Wheeler Street and CambridgePark Drive by the city’s contractor will continue with fine grading, asphalt base course, curb and sidewalk restoration, tree planting, and final paving. Parking on Wheeler Street and CambridgePark Drive will only be taken during the hours of construction (7AM to 4PM) on an as needed basis. No parking signs will be posted and updated.

Work in the Alewife Reservation continues with final planting, boardwalk construction, and multi-use path restoration. The city is expected to open the Alewife Reservation Wetland Basin to the public in September 2013.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

June 3, 2013

This week, the contractor will begin paving the new bike path in the wetland area. Once the bike path is complete, crews will begin to work on the construction of the amphitheater.

----------------------------------------------------------------------------------------------------------------------

May 16, 2013

The city’s contractor has completed installation of underground work for the project and will now focus on surface restoration. 

Surface restoration of Wheeler Street and CambridgePark Drive by the City’s contractor will start with fine grading, asphalt base course, curb and sidewalk restoration, tree planting, and final paving.  Parking on Wheeler Street and CambridgePark Drive will only be taken during the hours of construction (7AM to 4PM) on an as needed basis. No parking signs will be posted and updated. 

Work in the Alewife Reservation continues with final planting, boardwalk construction, and multi-use path restoration. The City is expected to open the Alewife Reservation Wetland Basin to the public in September 2013.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

April 24, 2013

Verizon completed their relocation of overhead cable from the east side of Wheeler Street to the west, including splicing, in January 2013. This allowed NSTAR Electric to remove their utility poles and the city’s contractor to continue underground utility work on Wheeler St.

The city’s contractor completed the final 300 feet of approx. 3300 feet of box culvert installation for the project. This milestone hydraulically connects Wheeler Street to the forebay of the stormwater wetland basin.

Restoration of Wheeler Street by the city’s contractor will start with an asphalt base course, curb and sidewalk restoration, tree planting, and final paving. Parking on Wheeler Street will only be taken during the hours of construction (7AM to 4PM) on an as needed basis. No parking signs will be posted and updated.

Work in the Alewife Reservation continues with boardwalk construction, and final planting.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

January 8, 2013

Underground utility work by the city's contractor will continue on Wheeler Street through the winter.  Verizon is completing the relocation of their cable from the easterly side of Wheeler Street to the westerly side and has almost completed their splicing work. NSTAR Electric will remove the utility poles from the east side of Wheeler Street when the Verizon cables are removed by Verizon. 

Work in the Alewife Reservation continues with boardwalk construction as weather permits.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

December 14, 2012

Construction on Wheeler Street will begin this Monday, December 17th. Please click on the "Documents" tab to view the official notice.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

October 2, 2012

The Oxbow is fully connected to the Little River.  Sandbags were removed from the banks allowing the river, fish and ducks to circulate through the Oxbow.  Grading and shaping continues on the wetland meadow south of the Oxbow and in the vegetated swale between the forebay and main basin.  Planting of upland shrubs and trees continues around the forebay and main basin.  Work on the boardwalk across the main basin to begin soon.

Utility work for water, AT&T, gas and electric continues near CambridgePark Drive.  Limited work has begun on Wheeler Street by Verizon to splice cables. 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

September 13, 2012

Planting of wetland plugs and forming of the wetland basin, vegetated swale and forebay is almost complete.  Forming and planting of the Oxbow is completed and soon the sand bags and silt curtains will be removed from the Oxbow inlet and outlet allowing Little River water to circulate through the Oxbow.

Excavation and grading has begun for construction of the base course for the bike path.  Grading of the upland areas between the bike path and the Oxbow and wetland basin has also begun. Planting of shrubs along the basin slopes will continue.

Work on Wheeler Street has been delayed pending the completion of work by Verizon.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

 August 13, 2012

In the reservation: excavation and grading of the main basin, planting in the wetland area, placement of footings for the boardwalk.  Work on the Belmont structure.

On Wheeler St: Verizon continues to work on their infrastructure for approximately 2 more weeks.

on CambridgePark Drive: Cambridge Water Dept responding to a leak at Smith Place on Monday, 8/13.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

July 23, 2012

In the reservation: grading of the main basin, planting in the oxbow, work on the Belmont structure.

 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -  

July 20, 2012

In the reservation: grading and planting continues in the oxbow, top soil screening on Lake St.

Verizon is pulling cable on Wheeler St.

 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -  

July 9, 2012

Members of the community are invited to join us for a public planting day at the new Alewife Wetland this Saturday, July 14.  Learn more

 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -  

June 26, 2012

In the reservation: grading and excavation continues at the oxbow, planting underway throughout the site.
On Cambridge Park Drive: box culvert complete; Verizon working on ducts
On Wheeler Street: conduit work Saturday, June 30th.  Verizon onsite at 55 Wheeler Street.
Abt property: curb work on-going
 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -  

June 21, 2012

Box culvert installation has been completed at 125 CambridgePark Drive.  Restoration of 125/150/180 Cambridge Park Drive and 55 Wheeler Street is ongoing.  Utility relocation within CambridgePark Drive continues with remaining box culvert installation to follow the raising of Verizon conduits.

Problems persist with Verizon's utility relocation on Wheeler Street.  Utility relocations and box culvert installation to begin immediately upon Verizon's cable relocation.

Grading and soil placement continues in the Alewife Reservation.  Planting has begun in the "Riparian Woodland" sections along the northern wetland edges.  The Oxbow has been dewatered and the area is being graded and soils placed.  See the "Photo" tab for images.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

May 17, 2012

Box culvert installation has been completed at 55 Wheeler Street and 150/180 CambridgePark Drive.  Restoration of these properties is underway.  Installation of the box culvert has begun at 125 CambridgePark Drive and will be followed by work within CambridgePark Drive to relocate existing utilities and installation of the box culvert and closing structure. 

Verizon will be relocating their cable from the east side of Wheeler Street to the west side of the street in preparation for the box culvert installation to occur within Wheeler Street from 55 Wheeler Street south to Concord Avenue.

Grading and soil placement continues in the Alewife Reservation for the forming of the stormwater wetland.  Footings have been completed for the boardwalk across the main basin and the overlook to the forebay area.  The forebay area is completed and the outfall headwall is installed.  Preparations are underway for the beginning of plantings.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

March 22, 2012

Box culvert installation across 55 Wheeler Street has been completed and temporary restoration of excavated areas to begin.  Night construction has ended and normal construction hours will be resumed.  Box culvert installation will begin across the parking lots at 150/180 CambridgePark Drive.

Test pits were performed along the length of Wheeler Street to determine an alignment for a new water main.

Work continues on the construction of the Belmont Crossing Structure that will allow the box culvert to pass over the MWRA interceptor pipes behind 125 CambridgePark Drive.

Forming and stabilization of the forebay to the Alewife Stormwater Wetland is 80% completed and work continues on grading of wetland and stabilizing berms around the perimeter of the future wetland.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

February 13, 2012 

Utility relocation on the 55 Wheeler Street property is substantially complete.  Box culvert installation has begun and is slightly ahead of schedule.  Box culvert installation on 55 Wheeler Street should continue through March.

Utility work and box culvert installation on Fawcett Street is substantially complete.

The Belmont Crossing Structure that will allow the box culvert to pass over the MWRA interceptor pipes behind 125 CambridgePark Drive is under construction.

Berm construction surrounding the wetland basin is substantially complete and work continues on grading areas of the forebay and oxbow.  Footings for an Oxbow overlook have been installed.  Site dewatering continues.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

December 13, 2011

A skim coat of asphalt has been applied to Wheeler Street in preparation for the relocation of existing utilities on property at 55 Wheeler Street. This skim coat of asphalt was applied to help reduce the noise from construction vehicles traveling along Wheeler Street.  Work to relocate existing utilities within the 55 Wheeler Street property is required to be completed prior to the installation of the box culvert through this property.  Utility relocation work on 55 Wheeler Street is anticipated to take 8 weeks, box culvert installation is scheduled immediately following. These construction activities should continue through April with surface restoration immediately following..  Construction on 55 Wheeler Street will occur Monday through Friday, between 2 pm through 11 pm.

Utility work and box culvert installation within Fawcett Street should be completed prior to the end of the 2011.

Excavation, screening, stockpiling and removal of soils continues within the Alewife Reservation.  Approximately 1/3 of the stormwater wetland berm has been installed..

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

November 17, 2011

The Wheeler Street paving that was scheduled for Friday, November 18 has been postponed.  Please check back for updates.  We apologize for any inconvenience.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

October 17, 2011

Vegetation within the Alewife Reservation has been cleared in preparation for construction of the stormwater wetland.  Current work activities include the continued work on electrical, water, sanitary and telecommunication lines.  An erosion control berm will be constructed to protect the work area. 

Utility relocation continues on Fawcett Street to make room for the installation of the box culvert through the turn near 70 Fawcett Street to the sections installed at the railroad crossing. 

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

October 3, 2011

The crossing of the high speed railroad lines near 70 - 110 Fawcett Street was successfully completed over the weekend from Friday, September 30 at 8:00 p.m. through Monday, October 3 at 5:00 a.m.  The box culvert, water main and approach slab was completed at this location and the high speed commuter rail lines were replaced and ready for commuter traffic on Monday morning.  Work will continue through the railroad property and into Fawcett Street where existing utility lines will be relocated to make room for the continuation of the box culvert work within Fawcett Street between the railroad and 70 Fawcett Street.  This work should take approximately 4 weeks to complete.

Clearing of vegetation within the Limit of Work area within the Alewife Reservation will begin on October 3rd to allow for the beginning phases of construction of the stormwater wetland.  Following clearing an erosion control berm will be established prior to excavation and grubbing.  Grubbing of the area will occur in phases as construction proceeds.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

September 21, 2011

NOTICE:  The work scheduled for the crossing of the high speed commuter railroad lines has been postponed and will not occur over the weekend from September 23rd to September 26th.  Work will be rescheduled and is tentatively set for the weekend of September 30th to October 2nd.  Please check here and on the MBTA website at http://mbta.com/rider_tools/transit_updates/  under “Service Updates - Commuter Rail”.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

September 19, 2011

Beginning on Friday, September 23 at 8:00 p.m. and continuing through Monday, September 26 at 5:00 a.m., the City of Cambridge’s contractor, P. Gioioso & Sons, in coordination with the MBTA, will be conducting construction work activities across the MBTA railroad tracks in the area north of Fawcett Street and south of CambridgePark Drive.

This work requires a shut-down of the inbound and outbound Fitchburg Commuter Rail Line during the weekend construction time period (9/23 to 9/26). Commuters will be directed to shuttle buses which will be operated by the MBTA between stations (inbound and outbound). Please refer to the MBTA’s web site for the most up to date information on busing, as routes may change: http://mbta.com/rider_tools/transit_updates/  under “Service Updates - Commuter Rail”. Please note that this work will not impact Red Line subway or MBTA bus service.

In order to complete these activities as quickly as possible, work will be conducted continuously on a 24-hour a day basis during Friday evening through early Monday morning. Construction vehicles will be accessing the work zone from Fawcett Street and CambridgePark Drive. Construction equipment will be operating for most of this time period. You may experience increased sounds of construction and notice lighting in the railroad area needed for construction night time operation. 

For more information, please view the community notice.

 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _  _ _ _ _

September 12, 2011

A community meeting was held to discuss the construction activities associated with the stormwater wetland construction on Wednesday, September 7th at 6:30 p.m. at the West Cambridge Youth Center, 680 Huron Avenue, Cambridge.  Click here to view a copy of the presentation.  The establishment of the construction work zone and erosion control placement will begin the week of September 12th.  A process to identify and relocate wildlife found within the work zone will continue along with the establishment of the work zone.  Clearing activities will begin within this work zone on or after October 1st. 

A pedestrian and bicycle detour between Belmont and the Alewife MBTA Red line Subway Station within the Alewife Reservation went into effect in June and will be in effect for the duration of the Alewife Reservation construction.  Please click here for a map of the detour area, route and schedule. 

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _  _ _ _ _

The Cambridge Department of Public Works in conjunction with NSTAR Electric, NSTAR Gas, and AT&T, began utility relocation work in the Alewife Reservation on Tuesday May 3, 2011 in advance of the start of the stormwater wetland construction. This utility work relocated utilities beneath a portion of the Alewife Reservation and Little River to Acorn Park Drive through a process called Pilot Tube Auger Boring (PTAB).  PTAB is a trenchless technology method designed to minimize disturbance in the Alewife Reservation and Little River by tunneling under the Little River.   For a demonstration of PTAB please see the following video on You Tube.  The PTAB portion of the utility relocations has been completed.  Remaining work includes open trenching of the underground utilities from the staging area south to the connection points to existing utilities adjacent to the existing bike path. This work is on-going and expected to be completed by the end of September 2011.

Flagging of wetlands and the survey of the Limit of Work area for the stormwater wetland has been completed and a Limit of Work construction fence is being erected and erosion control devices are being established beginning September 12th.  A community meeting was held on September 7th to discuss construction schedule and sequencing for the stormwater wetland (see above). For more information on the Stormwater Wetland design, schedule and bike/pedestrian detour please click here.

A second work crew continues the construction on the Bending Weir structure that will connect the existing 72" Wheeler Street drain to the proposed 8' x 4' box culvert.  The structure is located beyond the end of Wheeler Street adjacent to the Railroad tracks.  Another structure, MWRA crossing structure, is also under construction behind 70 Fawcett Street that will allow the new box culverts to pass over/around the existing MWRA pipes.

Construction of the box culvert beneath the railroad tracks near the bend on Fawcett Street will begin the evening of September 23rd.  Construction under the high speed commuter line tracks will be a 24 hour operation beginning the evening of September 23rd through the morning of September 26th.  During this time commuter rail service will be interrupted and busing of commuters will replace rail service. Pre construction activities have begun with the removal of freight lines near the bend in Fawcett Street by Pan Am Railways.  More information to follow.

Refer to the Schedule tab for more information on work activities.

 

Page was last modified on 7/25/2023 3:43 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.