Cambridge Tunnel Reconstruction Project

Includes the Cambridge St tunnel and the overpass area adjacent to Harvard Yard

This project has been completed. No further updates to this project page will be made.

December 1, 2014

The project has been completed.

-----------------------------------------------------------------------------------

November 17, 2014

Crews will continue working on asphalt transitions in and out of the tunnel and will perform line striping.  The tunnel is expected to completely reopen in the next 2 weeks.

-----------------------------------------------------------------------------------

November 10, 2014

Crews continue to monitor the curing process for the newly placed concrete and prepare for the asphalt transitions on the eastbound side of the tunnel. Crews will continue with the demobilization process this week.

--------------------------------------------------------------------------------------

October 27, 2014

On Thursday, October 30, the City’s contractor, MIG Corporation, will close the westbound portion of the Cambridge Street Tunnel (traveling towards Harvard Square), in order to place new concrete wearing surface. The westbound lanes will be closed from 4am – 3pm. Motorists travelling in the eastbound lanes will not be impacted. Message boards and detour signs will be highly visible during this closure. Emergency vehicles will maintain access at all times. Please click here to view detour.

-----------------------------------------------------------------------------------------------------------

October 20, 2014

Beginning at 11pm on Monday, October 20, the City’s contractor, MIG Corporation, will close the eastbound portion of the Cambridge Street Tunnel (Harvard Square towards Cambridge Fire Headquarters), in order to pour new concrete flooring. The eastbound portion of the tunnel will be closed from 11pm through 12pm on Tuesday, October 21. Motorists travelling in the westbound lanes will not be impacted. There will be a final westbound closure at the end of October, and we expect all construction activities to be complete in November. Please click here to view detour.

------------------------------------------------------------------------------------

September 22, 2014

This week, crews will begin to remove old concrete material from the existing lanes inside of the tunnel. There will be one lane closed in each direction.

--------------------------------------------------------------------------------------- 

June 20, 2014

Beginning the week of June 23, the City’s contractor, MIG Corporation, will mobilize crews to replace the 2” concrete overlay in the Cambridge Street Tunnel. The concrete overlay, which was installed in the summer of 2013, did not bond properly with the floor of the tunnel and began failing last fall. Over the winter and spring, sections of the overlay deteriorated and had to be replaced with temporary asphalt patches. Next week, the contractor will begin to remove the 2” concrete overlay, make any necessary repairs to the concrete base and then place the new concrete wearing surface. The work will be done in phases to maintain one travel lane in each direction of the tunnel, and is expected to be completed by September 2014.

--------------------------------------------------------------------------------------

 

Page was last modified on 7/25/2023 3:43 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.