November 2024:
No Work November 5th due to Election Day
No Work November 11th due to Veterans Day Holiday
No Work on November 28th and 29th Due to Thanksgiving Holiday
Week of November 4th: Raised Crossing Paving at Bristol, Seckle and at York
Week of November 11th: Raised Crossing Install at York St
Week of November 18th: Punch list items
Week of November 25th: Punch list items
Construction Notice: Final Roadway Milling and Paving week of October 28th.
The City’s contractor, Newport Construction, will be performing final roadway milling and paving on Webster Ave., from Hampshire Street to Lincoln Street the week of October 28.
The roadway grinding operation is expected to take two days (October 28 & 29) followed by paving of the roadway on Wednesday, October 30 and Friday, November 1, weather permitting. Wet weather on scheduled paving days will delay paving until the next dry day. Please visit the project page for any updates regarding rescheduling: www.cambridgema.gov/websterave.
Equipment that may be heard during paving operations will be, but not limited to, pavers, vibratory rollers, and vehicle back up alarms.
*Newly paved areas will be reopened to users as conditions allow, typically within a few hours of completion*
Any additional restoration items related to the project, including back of sidewalk work and pavement markings, will be completed by the contractor in the coming weeks before the end of construction. The addition of street trees is also part of this project and tree planting will take place at the end of the project during the spring planting season.
What to Expect during Paving
- General work hours will be 7 a.m. to 4 p.m., Monday-Friday.
- Parking will be restricted along the street for the duration of this work. Please be mindful of posted signage.
- Use caution on milled surface as castings will be raised.
- Motorcycles and bicycles use caution when traveling on milled surface.
- Vehicle access in and out of properties will be restricted during work hours while crews perform the paving. Please plan vehicle and parking trips accordingly.
- Access will be maintained for emergency vehicles and City services.
Information & Assistance:
If you have any questions about the project or the paving operations, please contact Kristen Kelleher, DPW Community Relations Manager, 617-349-4825/kkelleher@cambridgema.gov or Melissa Miguel, Supervising Engineer, 617-349-9351/mmiguel@cambridgema.gov. For more information about the project, visit www.cambridgema.gov/websterave. If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary. Thank you in advance for your patience and understanding during this construction.
In case of a construction emergency, please call the Cambridge Public Works Department 24-hour hotline at 617-349-4800.
October 2024:
Week of October 7: Curb and sidewalk work
NO WORK Monday, October 14, Indigenous Peoples' Day
Week of October 14: Curb and sidewalk work
Week of October 21: Curb and sidewalk work
Week of October 28: Mill and pave the roadway
September 2024:
Week of September 2: Curb and sidewalk work
NO WORK Monday, September 2, Labor Day or Tuesday, September 3, Voting Day
Week of September 9: Curb and sidewalk work (Hampshire to Lincoln)
Week of September 16: Curb and sidewalk work (Hampshire to Lincoln)
Week of September 23: Curb and sidewalk work (Hampshire to Lincoln)
Week of September 30: Curb and sidewalk work (Hampshire to Lincoln)
August 2024:
Week of August 5: Curb and sidewalk work (Hampshire to Plymouth)
Week of August 12: Curb and sidewalk work
Week of August 19: Curb and sidewalk work
Week of August 26: Curb and Sidewalk work (Hampshire to Lincoln)
July 2024:
Week of July 1: (no work July 4 or July 5) Curb and sidewalk work (Hampshire St to Plymouth St)
Week of July 8: Curb and sidewalk work
Week of July 15: Curb and sidewalk work
Week of July 22: Curb and sidewalk work
June 2024:
Week of June 10: Curb and sidewalk work begins (Hampshire St to Lincoln St)
Week of June 17: (no work on Juneteenth - June 19 Holiday) Curb and sidewalk work
Week of June 24: Curb and sidewalk work
Construction Notice: Webster Avenue Curb and Sidewalk work to begin June 11th
In association with the Webster Avenue Reconstruction Project, the City’s Contractor, Newport Construction., will begin to reconstruct the curb and sidewalk on Tuesday, June 11th. This work is anticipated to last for approximately six weeks, weather permitting.
At the end of each day, the contractor will clean the work site to allow for motorists to utilize the roadway. We kindly ask that motorists drive through the construction zone slowly outside of general working hours.
Work will begin on Webster Avenue from Hampshire St toward Lincoln St. The contractor will begin by removing the existing sidewalk material, and then removing / repositioning curbing based on the road design. Once the existing sidewalk is stripped and the curb is set, new sidewalks will be installed.
Detours will be in place during work hours. Please look for Detour signs, Road Closed signs, and No Parking signs as they will be changing frequently during the work.
What to Expect During Construction:
- General work hours 7am-4pm, Monday through Friday.
- Please check posted No Parking signs.
- During this work, the roadway will be lower, making the curbs higher for parked cars.Please use caution when opening car doors as to not damage them on the curbs.
- Access to properties will be maintained, when possible.
- Access will be maintained for City services and emergency vehicles.
Final roadway paving will occur at the end of the Webster Avenue project and will be announced via an additional notice in the coming months.
For Information and Assistance During Construction:
Questions regarding this project? Contact Kristen Kelleher, Community Relations Manager, at 617-349-4825 / kkelleher@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351 / mmiguel@cambridgema.gov. For more information about the project, visit https://www.cambridgema.gov/Departments/publicworks/cityprojects/2019/websteravenue. If you have any special needs or disabilities, please contact us to arrange for special accommodation that may be necessary.
January 2, 2024:
Construction Notice: Webster Avenue Reconstruction Project
As part of the Webster Avenue Reconstruction Project, the City’s contractor, Newport Construction, will begin mobilizing in the coming weeks.
Newport will begin installing tree protection along the street this week, followed by delivery and installation of drainage structures. DigSafe markings will also begin appearing on the sidewalk and roadways.
This work will take approximately 8 weeks to complete.
Full depth roadway reconstruction, curb resetting, sidewalk installation, and final paving will happen later this year and you will receive an additional notice prior to this work beginning.
The addition of street trees is also part of this project and planting will take place at the end of the project during either the fall or spring planting season.
What to expect during construction:
- Work Hours will be 7:00 a.m. to 4:00 p.m. Monday-Friday.
- "No Parking" signs will be posted; please be sure to check dates/times.
- We understand the impacts to business parking and loss of parking will be kept to a minimum.
- Vehicle access in and out of properties will be maintained but may be restricted for short periods. If you need access and your driveway is blocked, please speak to a crew member on site and they will make accommodations for you.
- Emergency vehicles and City service vehicles will have access at all times.
Information & Assistance:
Questions regarding this project? Contact Kristen Kelleher, Community Relations Manager, at 617-349-4825/ kkelleher@cambridgema.gov or Melissa Miguel, P.E. Supervising Engineer, at 617-349-9351/ mmiguel@cambridgema.gov. If you have a special need or disability, please contact us to arrange for accommodations that may be necessary. In case of an emergency after hours, please call the 24-hour line at 617-349-4800.
September 2022:
Bidding for this project was delayed. The bid is now open until October 6, 2022.
September 2021:
Design plans are being finalized and the project is expected to go out to bid in Fall 2021. More updates, including a more detailed timeline, will be provided once a contractor is on board.
Notice: Webster Ave. Reconstruction Project Community Meeting Wednesday, February 26th
Webster Ave, between Lincoln St. and Hampshire St., is scheduled for upcoming street and sidewalk reconstruction as part of the City’s 5 Year Plan.
The Department of Public Works and the City’s Community Development Department will be hosting a second community meeting on Wednesday, February 26th from 6PM-7:30PM at the Valente Library Program Room, 826 Cambridge Street to discuss the Webster Ave. Reconstruction Project.
City staff would like to discuss preliminary designs for traffic calming and safety improvements for the street. These designs were developed after receiving feedback at the first community meeting held Tuesday, April 23rd 2019. We encourage you to attend, as we value the feedback we receive from Cambridge residents and businesses.
Information and Assistance:
The City of Cambridge does not discriminate on the basis of disability. The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request. To receive future updates via email, please contact Kate Riley, Communications Manager at kriley@cambridgema.gov / 617.349.4870. For information about the project please contact Melissa Miguel, Supervising Engineer at mmiguel@cambridgema.gov. For traffic calming information contact Juan P. Avendano, Community Development Project Manager, at 617. 349.4655 / javendano@cambridgema.gov.
Notice: Chapter 90, Contract 24 - Catch Basin Inspections
As part of the continued design process, crews will be inspecting catch basins beginning Tuesday 11/12. "No Parking" signs will be posted 48 hours in advance. Work will last approximately 1-2 days at each location.
Please note, the work referenced below has been postponed until September 4th.
Notice: Chapter 90, Contract 24 – Road Reconstruction of Park Ave., Webster Ave., Chestnut St., Dodge St. and Elm St.
As the design team continues their work, Briggs Engineering is scheduled to begin the pavement analysis on the Contract 24 Streets on Wednesday 8/28/2019. The working will include obtaining pavement cores and conducting small test pits, approximately 2’ by 2’, to obtain gravel samples below the pavement. Please take note of "No Parking" signs posted 48-hours in advance.
Notice: Webster Ave. Reconstruction Project Community Meeting
Webster Ave, between Lincoln St. and Hampshire St., is scheduled for upcoming street and sidewalk reconstruction as part of the City’s 5 Year Plan.
The Department of Public Works will be hosting a community meeting on Tuesday, April 23rd from 6PM-7:30PM at the Frisoli Youth Center located at 61 Willow Street. to discuss the Webster Ave. Reconstruction Project.
The project is part of the City’s Complete Streets initiative to design and operate streets that are safe for all users including pedestrians, cyclists, motorists and public transit users. The focus of this meeting will be to discuss the design and construction process and solicit feedback from the community. We encourage you to attend, as we value the feedback we receive from Cambridge residents and businesses.
Information and Assistance:
The City of Cambridge does not discriminate on the basis of disability. The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request. For more information, please contact Melissa Miguel, Supervising Engineer, at 617.349.9351/ mmiguel@cambridgema.gov. To receive future updates via email, please contact Kate Riley, Community Relations Manager, at kriley@cambridgema.gov / 617.349.4870.
Notice: Chapter 90, Contract 24: Road Reconstruction of Park Ave., Webster Ave., Chestnut St., Dodge St.
As part of the design process for roadway reconstruction of your street, the City's contractor Kleinfelder and their subcontractors, will begin field work which may include subsurface investigations, topographical survey, utility inspections, etc. The purpose of these investigations is to obtain existing pavement, utility, and soil/groundwater conditions. The results will assist in developing a complete street design for your street. Initial existing conditions survey will be presented at upcoming community meetings where residents will have the opportunity to provide input.
Residents will notice DigSafe marks in the area and should be are of No Parking signs. Subsurface investigation locations have been selected in areas that will give the best representation of roadway conditions while minimizing traffic and parking disruptions where possible. However, "No Parking" areas will still be designated. "No Parking" signs will be posted 48 hours in advance.
The impacted streets are:
- Park Avenue – Huron Ave to Holworthy St
- Webster Avenue – Lincoln St to Hampshire St
- Chestnut Street – Sydney St to Pleasant St
- Dodge Street – Western Ave to Callender St
All work is part of the early design phase and residents will be notified of all community meetings and any upcoming construction work as the project progresses.
Thank you for your patience as we work to improve your street.
What to Expect:
- Work hours will be 7 AM to 4 PM, Monday-Friday.
- “No Parking” signs will be posted; please be sure to check dates/times.
- Emergency vehicles and city services will have access at all times.
Information & Assistance:
Questions regarding this project? Contact Kate Riley, Community Relations Manager, at 617.349.4870/
kriley@cambridgema.gov. If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary.
For updated project information and to join the project email notification list please visit the
City construction projects list.