U.S. flag

An official website of the United States government

Cambridge Common and Flagstaff Park

The Cambridge Common and Flagstaff Park project aims to rehabilitate all aspects of the Common as well as improve conditions for all users of these parks and those travelling along this section of Mass. Avenue, from Garden Street to Cambridge Street. It also seeks to unify the historic landscape of the Common by simplifying the vocabulary of the design. The planning of the project has been underway for many years, along with securing funding for the nearly $4m project. The project will replace all pathway surfaces on the Common to meet access codes with bituminous paving with a brick edge, replace and upgrade all benches and trash cans, plant over 100 trees and remove older under-story plantings, improve drainage and turf surfaces, and rehabilitate the lighting system to extend its life and add lighting to pathways where it is missing.

Across the street, along the Mass. Avenue side of Flagstaff Park, the curbs will be moved out and a two-way multi-use path constructed with crossings at each end to create better bicycle and pedestrians connections between Harvard Square and Mass. Avenue northbound.

This project has been completed. No further updates to this project page will be made.

The project is now complete.


June 20, 2016

  • Crews are working on final punch list items.
  • All major construction activities are complete.

_________________________________________________________________________________________________________________________________________________________________


June 6, 2016

  • Crews will continue with irrigation work
  • All significant construction activities are complete

_________________________________________________________________________________________________________________________________________________________________


May 2, 2016

  • Brick work around the cannons will be complete this week.
  • Crews will continue working on the field installing new soil.
  • Irrigation will be installed later this week.


___________________________________________________________________________________________________________________________________________________________________


March 30, 2016

  • Brick work around the monuments is almost complete.
  • Field loaming and landscaping will begin in April.
  • All pathways are complete and open to the public.
  • Construction activities are expected to be complete by the end of May.


___________________________________________________________________________________________________________________________________________________________________



Winter 2016

  • Improvements within the Common will be ongoing throughout the winter, mainly brick work around the monument, weather dependent.
  • All pathways completed.
  • Irrigation piping, cobblestone strip, and wood rail fence being installed along Garden St and should be complete in February.
  • Brick and granite pavers being installed around the monument.
  • Majority of benches have been installed and Big Belly trash/recycling receptacles will be installed upon delivery.
  • Additional seeding and planting to take place in Spring 2016.
  • Project includes improved pathways within the Cambridge Common, new benches, trash and recycling receptacles new trees and grass, improved playing fields and irrigation.
  • Ballfield area to be completed: Spring 2016.
  • Scheduled to be completed: Spring 2016.


October 9, 2015

Cambridge Common & Flagstaff Park
Construction Update
*Please note the following anticipated schedule is weather dependent*

Anticipated Completion - Fall 2015:

  • All Pathways and Plaza Areas
  • Pathway Lighting
  • Perimeter Curbing and Cobblestone Pavement
  • Post and Rail Fence
  • Parking Meters
  • Site Furnishings: Benches, Bicycle Parking, Trash and Recycling Receptacles
  • Perimeter Tree Planting

Anticipated Completion - Spring 2016:

  • Kiosk and Signage
  • Remaining Tree Planting (Interior Trees)
  • Irrigation
  • Lawn Seeding and Establishment

MassDOT and the City of Cambridge appreciate your patience.

For any questions, please contact MassDOT supervising engineer, Claude Noailles at 617-222-0008 or claude.noailles@state.ma.us


October 2015

  • Improvements within the Common will be ongoing throughout the fall. The Mass Ave road work is complete.
  • Pedestrian pathways remain under construction, however the path adjacent to the Tot Lot is now open.
  • Pedestrian access to the path adjacent to the cannons, from Garden St to Mass Ave, will be closed for the next several weeks while work is completed.
  • Irrigation piping began this week along Mass Ave.
  • Tree planting and seeding to take place from October through Thanksgiving, weather permitting.
  • Installation of cobblestones around the monument to begin 9/28, weather permitting.
  • Additional seeding and planting to take place in Spring 2016.
  • Project includes improved pathways within the Cambridge Common, new benches, trash and recycling receptacles new trees and grass, improved playing fields and irrigation.
  • Pathways to be completed: Fall 2015
  • Tree Plantings to be competed: Fall 2015 and Spring 2016
  • Ballfield area to be completed: Spring 2016
  • Scheduled to be completed: Spring 2016

September 2015

  • Pedestrian pathways remain under construction, however the path adjacent to the Tot Lot is now open. Pedestrian access to the path adjacent to the cannons, from Garden St to Mass Ave, will be closed for the next 2 weeks while work is completed.
  • Tree planting and seeding to take place from October through Thanksgiving, weather permitting.
  • Installation of cobblestones around the monument to begin 9/28, weather permitting.
  • Additional seeding and planting to take place in Spring 2016.

August 2015

Flaggstaff Park is currently open. The new path allows users to ride their bicycles of enjoy a run or walk through the park. This month crews will be working on the pedestrian paths within the Cambridge Common.

Page was last modified on 7/25/2023 3:43 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.