U.S. flag

An official website of the United States government

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Land Boulevard Infrastructure Improvements Project

Infrastructure improvement project at the intersection of Land Boulevard and Binney Street.

This project has been completed. No further updates to this project page will be made.


December 5, 2013

The project has been completed.

----------------------------------------------------------------------------------------------------------------------

November 18, 2013

Crews are approximately 90% complete with the project. The City's contractor is currently performing punch list items to complete the project.

----------------------------------------------------------------------------------------------------------------------

November 4, 2013

Paving operations in the project area have been completed. Crews are now working on punch list items to complete the project.

----------------------------------------------------------------------------------------------------------------------

October 28, 2013

 On Tuesday, October 29, the city’s contractor, P. Caliacco Corp., will mill the intersection of Land Blvd and Binney St to prepare the roadway for paving. Work hours will be 7 AM to 4 PM. Paving is scheduled for Thursday, October 31, weather permitting. Land Blvd will remain open during milling operations on Tuesday; eastbound traffic on Binney St will be detoured to First St during work hours. Roadway paving operations will take place on Thursday, October 31. Both roadway operations are expected to cause minor delays for motorists.

--------------------------------------------------------------------------------------------------------------------------------------------------

October 22, 2013

Crews are currently performing sidewalk work and cleaning up the project area. Roadway paving operations are expected to begin early next week.

--------------------------------------------------------------------------------------------------------------------

October 8, 2013

This week, crews will be placing binder material down on the roadway in preparation for final paving. Another crew will be performing sidewalk work, and the last crew will be working on the installation of the new traffic signals.

-------------------------------------------------------------------------------------------------------------------------------------------------

September 23, 2013

Crews will be onsite this week to install new roadway curbing in the project area.

--------------------------------------------------------------------------------------------------------------------

September 16, 2013

This week, crews will be prepping the worksite in advance of the curb resetting operation.

--------------------------------------------------------------------------------------------------------------------

September 3, 2013

Crews continue to work in the installation of traffic lights on Land Blvd. Another crew will begin to widen the island on the south side of Land Blvd.

-------------------------------------------------------------------------------------------------------------------------------------------------

August 26, 2013

Crews continue to work in the installation of traffic lights on Land Blvd.

--------------------------------------------------------------------------------------------------------------------

August 19, 2013

This week, crews will begin the installation of traffic lights on Land Blvd.

--------------------------------------------------------------------------------------------------------------------

June 17, 2013

This week, crews will be working on the installation of bending weir three (3).

--------------------------------------------------------------------------------------------------------------------

June 10, 2013

Crews are completing the installation of bending weirs one (1) and two (2). Installation for bending weir three (3) will begin later this week.

--------------------------------------------------------------------------------------------------------------------

May 28, 2013

Crews are continuing work on the bending weir structure on Land Blvd near Binney St. 

-------------------------------------------------------------------------------------------------------------------------------------------------

March 8, 2013

To view the recent update notice to the community, please visit the "Documents" tab.

--------------------------------------------------------------------------------------------------------------------

March 5, 2013

Crews are making progress on the Land Boulevard Infrastructure Project. Due to unforeseen utility conflicts within the project work zone, the City’s Contractor, P. Calicacco Corp., has subsequently pushed back the expected completion date to October 2013. To view the official notice, please visit the "Documents" tab.

--------------------------------------------------------------------------------------------------------------------------------------------------

February 21, 2013

Crews are currently setting up a long term work zone at the intersection of Binney St. and Land Blvd. (closest to the water), as the contractor will need to excavate in order to install two (2) bending weir structures. Lane closures will occur on Land Blvd. and so we ask motorists to be alert that the travel lanes may be modified. Signs will be posted onsite to make the travel lane modification as transparent as possible.

---------------------------------------------------------------------------------------------------------------------

November 19, 2012

Crews will be out paving sections of Land Blvd.

----------------------------------------------------------------------------------------------------------------------------------------------------

November 12, 2012

The contractor is continuing drain and sewer work across Land Boulevard to the Esplanade Building. 

-----------------------------------------------------------------------------------------------------------------------------------------------------

OCTOBER 29, 2012

Weather permitting, the contractor is continuing drain and sewer work across Land Boulevard to Esplanade Building.  Last Monday, October 15th, a long-term work zone was established. Binney Street will remain closed with a detour down First Street.

 

 

Project Schedule

 
Winter-Spring 2012 Utilities Relocation

 
Spring 2012-Fall 2012 Bending Weir Construction

 
Fall 2013 Surface Restoration

 

Project Background


The Cambridge Department of Public Works is constructing a project at the intersection of Land Boulevard and Binney Street during 2012. The purpose of this project is twofold; (1) to provide an outfall to the proposed sewer separation project on Binney Street and (2) to provide flood relief during significant rainfall events to the Area 4 neighborhood and the Central Square area.

Drainage from a 610 acre area to the west drains towards Land Boulevard and Binney Street. This combined sewer system services the Area 4 neighborhood, the Mid Cambridge neighborhood as far as Cambridge Hospital and most of East Cambridge. During larger rainfall events severe flooding and sewer backups occur throughout the Area 4 neighborhood and parts of East Cambridge. To relieve this flooding, the Department of Public Works has developed a facilities plan that includes twelve construction projects. These projects include sewer separation, large scale stormwater storage systems and combined sewer relief structures throughout the area. This project is the second of a number of projects that will be constructed throughout the neighborhood to provide relief.

Beneath this intersection, there presently exists a critical flood control structure called the CAM 017 regulator. During intense rainfall events when the conveyance capacity of the municipal and metropolitan drainage systems is overwhelmed combined sewage discharges to the Charles River at various regulator structures throughout the city such as the CAM 017 structure. These discharges are regulated by US EPA.

The objective of this construction project is to modify the CAM 017 structure so as to further relieve flooding upstream of this location. This will involve the construction of a new stormwater outfall adjacent to the regulator and the reconstruction of the CAM 017 structure, which will provide greater flood relief during extreme rainfall events.

Design for this project is being managed by the Cambridge Department of Public Works, in coordination with MWRA and the Department of Conservation and Recreation (DCR). Engineering consultants are MWH Americas Inc.

What to Expect during Construction 
    • Contractor will set secure Work Zones using Jersey barriers and drums. 
    • Installation of Temporary Excavation Support System 
    • Open cut excavation: Saw cut pavement; Excavators and dump trucks (load and go); move excavated soil off site; plate over open excavations at end of day. 
    • Street open to traffic at all times. Reduced to one lane. Police details to direct traffic flow. Access and egress for emergency vehicles will not be impeded.

Construction Impacts and Mitigation 
    •  Vibration and Noise: Day work to minimize disruption to residences. Contractor will monitor vibration and noise levels during construction. 
    • Dust and Debris: Contractor will monitor dust levels and implement dust control measures such as suppression with water or calcium     chloride. 
    • Deliveries: Special provisions will be made by building management.

Cambridge Department of Public Works 147 Hampshire Street

General work hours will be 7 AM to 4 PM with some extended hours during the project.

 

For information or assistance related to construction, please contact Lou Mothon, DPW Project Manager at 617.293.3305 or lmothon@cambridgema.gov.

You may also contact Kelly Dunn, Community Relations Manager, at 617.349.4870 or kdunn@cambridgema.gov

For 24-hour emergency assistance please call DPW at 617.349.4800.

Page was last modified on 7/25/2023 3:43 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.