This project has been completed. No further updates to this project page will be made.
August 21, 2017
The paving scheduled for Tuesday, August 22nd has been rescheduled for Wednesday, August 23rd, weather permitting.
August 17, 2017
The City’s contractor, P Gioioso & Sons, will pave roadway on Newport Rd and Roseland St on Tuesday, August 22, weather permitting. We expect the paving to take 1 day to complete.
Vehicle access in and out of properties will be restricted during work hours while crews perform the paving. Please plan vehicle trips accordingly.
Project Schedule
• On Tuesday, August 22, crews will pave Newport Rd and Roseland St. This is the final paving.
• We expect the paving to take 1 day to complete.
• Please note that paving is weather dependent and will be rescheduled due to heavy rain.
What to Expect during Paving
• Work hours will be 7 AM to 5 PM.
• Newport Rd and Roseland will be closed to through traffic during paving.
• Vehicle access in and out of properties will be restricted. Please plan vehicle and parking trips accordingly.
• “No Parking” signs will be posted; please be sure to check dates/times.
• Emergency vehicles will have access at all times.
July 24, 2017
Crews will begin construction of a raised intersection at Roseland and Frost Sts this week. During this time, Frost St will function as a two-way dead end while crews perform the work. We expect the new intersection to be complete by Wednesday or Thursday, weather permitting.
_____________________________________________________________________________________________________________________________________________________________
July 17, 2017
Crews will continue sidewalk reconstruction on Newport Rd. We expect the work to be completed by the end of this week. Crews will then begin the raised intersection at Roseland St and Frost St.
__________________________________________________________________________________________________________________________________________________________
July 10, 2017
Crews are continuing sidewalk reconstruction on Newport Rd.
_________________________________________________________________________________________________________________________________________________________
June 19, 2017
Crews are completing sidewalks on Roseland St. During the week of June 26, crews will move to Newport Rd to begin sidewalk reconstruction.
__________________________________________________________________________________________________________________________________________________________
June 5, 2017
Sidewalk reconstruction on Roseland St is ongoing. We expect crews to move to Newport Rd during the week of June 26 to begin sidewalks.
___________________________________________________________________________________________________________________________________________________________
May 8, 2017
Sidewalk reconstruction will begin on Roseland St during the week of May 15. Once crews complete the Roseland St sidewalks, they will move to Newport Rd.
____________________________________________________________________________________________________________________________________________________________
May 1, 2017
Crews will pave Roseland St and Newport Rd on Tuesday, May 2. This is binder paving; final paving will take place after the sidewalks are complete.
_______________________________________________________________________________________________________________________________________________________
April 24, 2017
Crews will perform roadway reconstruction this week on Newport Rd. Binder paving on Newport Rd and Roseland St is tentatively scheduled for Wednesday, May 3
______________________________________________________________________________________________________________________________________________________
April 10, 2017
Crews are completing the utility work this week. We expect roadway reconstruction on Roseland St to start next week.
________________________________________________________________________________________________________________________________________________________
April 3, 2017
Crews are expect to complete the water work this week, then begin catch basin installation.
________________________________________________________________________________________________________________________________________________________
March 27, 2017
Crews will continue working on the water main this week. We expect the water work to take one more week to complete, then crews will install 2 new catch basins. Crews will then move to Roseland St in mid-April to begin surface improvements.
_________________________________________________________________________________________________________________________________________________________
March 20, 2017
Crews are working on the water main this week. We expect this to continue into next week.
__________________________________________________________________________________________________________________________________________________________
March 13, 2017
Crews will install 2 new sewer manholes this week on Newport Rd, near Mass Ave. There will not be any construction activities on Tuesday, March 14 due to the storm.
___________________________________________________________________________________________________________________________________________________________
February 27, 2017
Crews are currently working on Newport Rd, near the intersection of Forest St performing sewer upgrades.
____________________________________________________________________________________________________________________________________________________________
February 21, 2017
Crews have mobilized on Newport Rd to begin utility work (work work will be first)
Please check back for updates.