Elm St Reconstruction Project

Elm St., between Webster Ave. and Hampshire St., is scheduled for upcoming street and sidewalk reconstruction as part of the City’s 5 Year Plan.


December 2024: 

No work on December 24 and 25, Christmas Holiday

No work on December 31 and January 1, New Year's Holiday

Week of December 2: Punch list items and miscellaneous sidewalk work

Week of December 9: Punch list items and miscellaneous sidewalk work

Week of December 16: Punch list items and miscellaneous sidewalk work

Week of December 23: Punch list items and miscellaneous sidewalk work

Week of December 30: Punch list items and miscellaneous sidewalk work


November 2024:

No Work November 5, Election Day

No work on November 11, Veterans Day Holiday

No work on November 28 and 29, Thanksgiving Holiday

Week of November 4th: Sidewalk work and Flexi-pave install 

Week of November 11th: Punch list items and castings to binder 

Week of November 18th: Punch list items, raised crossing installation and sidewalk work

Week of November 25th: Punch list items


CONSTRUCTION NOTICE: Base Paving Scheduled for Friday, October 4

The City’s contractor, Newport Construction, will be placing a base layer of asphalt on Elm Street between Hampshire Street and Webster Avenue on Friday, October 4th.

Work is expected to take approximately one day to complete, weather permitting. If conditions are wet on the day of scheduled paving, work will be delayed. Please visit the project page for any updates regarding rescheduling at www.CambridgeMA.gov/ElmStreet.

The roadway will also be lower, making the curbs higher for parked cars. Please use caution when opening car doors so as not to damage them on the curbs.

What to Expect During Construction:

  • General work hours are 7 a.m. – 4 p.m., Monday through Friday
  • Please check posted No Parking signs
  • Access will be maintained for abutters whenever possible. Caution should be used. After work hours, roadways will reopen for all in their normal travel directions.
  • Access will be maintained for City services and emergency vehicles.

Final roadway paving will occur at the end of the Elm Street Reconstruction Project and will be announced via an additional notice.

For Information and Assistance During Construction:

Questions regarding this project? Contact Kristen Kelleher, Community Relations Manager at 617-349-4825 / kkelleher@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351 / mmiguel@cambridgema.gov. For more information about the project and to sign up for the project email list, visit www.CambridgeMA.gov/ElmStreet. If you have any special need or disability, please contact us to arrange for special accommodation that may be necessary.


October 2024:

Week of September 30:  Full-depth Reconstruction (Hampshire Street to Webster Ave)

Week of October 7:  Curb and sidewalk work (Hampshire Street to Cambridge Street), Water services (Cambridge Street to Webster Ave)

Week of October 14 (No work on Monday, Indigenous Peoples Day):  Curb and sidewalk work (Hampshire Street to Cambridge Street), Water services (Cambridge Street to Webster Ave)

Week of October 21:  Curb and sidewalk work (Hampshire Street to Cambridge Street), Water services (Cambridge St to Webster Ave).

Week of October 28:  Curb and sidewalk work (Hampshire Street to Cambridge Street). 


Updated Construction Notice: Roadway Reconstruction to begin Week of 9/30

As part of the ongoing Elm St. Reconstruction Project, the City's Contractor, Newport Construction, will begin to reconstruct the roadway on Elm St. (Hampshire St. to Cambridge St./Cambridge St. to Webster Ave) beginning the week of September 30.

To ensure that the roadway conditions will be favorable for many years to come, crews will engage in full-depth reconstruction. At the end of each day, the contractor will clean the work site to allow for motorists to utilize the roadway. We kindly ask that motorists drive through the construction zone slowly outside of general working hours.

The full-depth reconstruction phase of the project is expected to take approximately 1 week to complete, weather permitting. Work will begin on Elm St. from Hampshire St. to Cambridge St./Cambridge St. to Webster Ave. The contractor plans to complete full-depth excavation, then place a base layer of pavement.

After full-depth reconstruction is complete, beginning the week of 10/7, the Contractor will begin the curb and sidewalk work phase (removing existing sidewalks, removing and resetting curb, and installing new ADA Compliant sidewalks). The Curb and sidewalk phase is expected to take approximately 3 weeks to complete, weather permitting.

Detours will be in place during work hours. Please look for Detour signs, Road Closed signs, and No Parking signs as they will be changing frequently during the work.

What to Expect During Construction:

  • General work hours 7am-4pm, Monday through Friday
  • Please check posted No Parking signs.
  • Removal of posted No Parking signs can add extensive time to the contract.
  • During this work, the roadway will be lower, making the curb reveal higher for parked cars. Please use caution when opening car doors as to not damage them on the curbs.
  • Access to properties will be maintained, when possible.
  • Access will be maintained for City services and emergency vehicles.

The final roadway paving phase will occur in the spring and will be announced via an additional notice. Please note that final paving does not mean the project is complete. There are small repair items that remain on these projects that must be addressed by the contractor.

For Information and Assistance During Construction:
Questions regarding this project? Contact Linda Spencer, Project Administrator-Community Relations at 617-349-9734/ lspencer@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351/ mmiguel@cambridgema.gov. For more information about the project, visit www.CambridgeMA.gov/ElmStreet. If you have any special needs or disabilities, please contact us to arrange for special accommodation that may be necessary.


Construction Notice: Roadway Reconstruction to begin week of 9/30

As part of the ongoing Elm St. Reconstruction Project, the City’s Contractor, Newport Construction, will begin to reconstruct the roadway on Elm St. (between Hampshire St. and Cambridge St.) beginning the week of September 30th

To ensure that the roadway conditions will be favorable for many years to come, crews will engage in full-depth reconstruction. At the end of each day, the contractor will clean the work site to allow for motorists to utilize the roadway. We kindly ask that motorists drive through the construction zone slowly outside of general working hours.

The full-depth reconstruction phase of the project is expected to take approximately 1 week to complete, weather permitting. Work will begin on Elm St. from Hampshire St. toward Cambridge St. The contractor plans to complete full-depth excavation, then place a base layer of pavement.

After full-depth reconstruction is complete, beginning the week of 10/7, the Contractor will begin the curb and sidewalk work phase (removing existing sidewalks, removing and resetting curb, and installing new ADA Compliant sidewalks). The Curb and sidewalk phase is expected to take approximately 3 weeks to complete, weather permitting.

Detours will be in place during work hours. Please look for Detour signs, Road Closed signs, and No Parking signs as they will be changing frequently during the work.

What to Expect During Construction:

  • General work hours 7am-4pm, Monday through Friday.
  • Please check posted No Parking signs.
    • Removal of posted No Parking signs can add extensive time to the contract.
  • During this work, the roadway will be lower, making the curb reveal higher for parked cars. Please use caution when opening car doors as to not damage them on the curbs.
  • Access to properties will be maintained, when possible.
  • Access will be maintained for City services and emergency vehicles.

The final roadway paving phase will occur in the spring and will be announced via an additional notice. Please note that final paving does not mean the project is complete. There are small repair items that remain on these projects that must be addressed by the contractor.

For Information and Assistance During Construction:

Questions regarding this project? Contact Linda Spencer, Project Administrator-Community Relations at
617-349-9734/ lspencer@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351/ mmiguel@cambridgema.gov. For more information about the project, visit www.CambridgeMA.gov/ElmStreet. If you have any special needs or disabilities, please contact us to arrange for special accommodation that may be necessary.


Construction Notice: Overnight water work scheduled for the Week of September 9–14

The City's contractor, Newport Construction, has been granted a Noise Variance Permit #284989 to conduct necessary water work at Cambridge Street and Elm Street on September 9-14 during the hours of 6 p.m.-7 a.m.


September 2024:

Week of September 2:  Water main work (Hampshire Street to Cambridge Street)

NO WORK on Monday, September 2, Labor Day or Tuesday, September 3, Voting Day

Week of September 9:  Water main work (Hampshire Street to Cambridge Street), overnight night work per Noise Variance

Week of September 16:  Water main work (Hampshire Street to Cambridge Street)

Week of September 23:  Water main work (Hampshire Street to Cambridge Street)

Week of September 30:  Full-depth Reconstruction (Hampshire Street to Cambridge Street)


August 2024:

Week of August 5:  Water main work (Lincoln Street to Cambridge Street)

Week of August 12:  Water main work (Lincoln Street to Cambridge Street)

Week of August 19:  Water main work (Lincoln Street to Cambridge Street)

Week of August 26: Water main work


July 2024: 

No work July 4 - 6 due to holiday

Week of July 1: Drainage work 

Week of July 8: Drainage work

Week of July 15: Water main work

Week of July 22: Water main work

Week of July 29: Water main work


June 2024: 

Week of June 3:  Drainage work continues

Week of June 10:  Drainage work continues, trench milling (Hampshire Street to Cambridge Street)

Week of June 17: (no work on Juneteenth, June 19 Holiday) Drainage work continues

Week of June 24:  Water work


MAY 2024:

Week of May 28:  Excavating and installing of new drainage structures begins


Construction Notice: Drainage work and Water work to begin May 28

As part of the Elm Street Reconstruction Project, the City’s contractor, Newport Construction, will mobilize on Tuesday, May 28th to begin excavating and installing new drainage structures. Crews will work primarily between Hampshire Street and Webster Avenue.

Following drainage work, weather permitting, Newport will begin the installation of the water main along Elm Street. Residents will receive a notice with specific details regarding this work.

The Drainage and water work is expected to last approximately 12 weeks, weather permitting.

The Elm Street Reconstruction Project is part of the City’s 5-Year Plan for Streets and Sidewalks, and will include paving, sidewalk work, and pedestrian ramp installations.

Detours will be in place during work hours. Please look for Detour signs, Road Closed signs, and No Parking signs as they will be changing frequently during the work.

What to Expect During Construction:

  • General work hours will be 7am – 4pm, Monday-Friday.
  • Please check posted No Parking signs.
  • Please follow pedestrian detour signs.
  • Access to properties will be maintained, when possible.
  • Access will be maintained for emergency vehicles and City services.

Information & Assistance:

Questions regarding this project? Contact Kristen Kelleher, Community Relations Manager, at 617-349-4825/kkelleher@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351/ mmiguel@cambridgema.gov. For more information about the project, visit www.CambridgeMA.gov/ElmStreet. If you have any special needs or disabilities, please contact us to arrange for special accommodation that may be necessary.


Notice: Tree Protection and Exploratory Excavation Beginning Monday, April 29

As part of the upcoming Elm Street Reconstruction Project, the City’s contractor, Newport Construction, will mobilize on Monday, April 29th to begin installing tree protection, as well as beginning some excavation work on the street. Crews will work primarily between Hampshire Street and Webster Avenue.

This work is expected to take approximately 1 week to complete, weather permitting

Detours will be in place during work hours. Please look for Detour signs, Road Closed signs, and No Parking signs as they will be changing frequently during the work.

What to Expect During Construction:

• General work hours will be 7am – 4pm, Monday-Friday.
• Please check posted No Parking signs.
• Please follow pedestrian detour signs.
• Access to properties will be maintained, when possible.
• Access will be maintained for emergency vehicles and City services.

Information & Assistance:

Questions regarding this project? Contact Kristen Kelleher, Community Relations Manager, at 617-349-4825 / kkelleher@cambridgema.gov or Melissa Miguel, Supervising Engineer, at 617-349-9351 / mmiguel@cambridgema.gov. For more information about the project, visit www.CambridgeMA.gov/ElmStreet. If you have any special needs or disabilities, please contact us to arrange for special accommodation that may be necessary.


September 2022:

Bidding for this project was delayed. The bid is now open until October 6, 2022. 


Community Presentation for the Elm Street Reconstruction Project

The video presentation for the community meeting on Wednesday, December 16th is now available to view. Residents who wish to submit questions in advance of the meeting may do so to kriley@cambridgema.gov. Advance questions, as well as new questions received “live”, will be answered during the meeting.

 

To view the video in full screen: http://https//youtu.be/FoSEiP198sk

Community Meeting Notice: Wednesday, December 16, 2020 at 6PM

Elm Street, between Hampshire Street and the Cambridge City line, is scheduled for roadway and sidewalk reconstruction.

We invite you to join us on Wednesday, December 16th from 6pm to 7:30pm for a virtual community meeting to review the proposed reconstruction plans, discuss project schedule, and answer questions.

The meeting can be accessed through this link:
https://cambridgema.zoom.us/j/82437814607
• Dial in: US: +1 312 626 6799
• Meeting ID: 824 3781 4607


These plans were developed after a community meeting with residents held on October 15, 2019. We encourage you to attend, as we value the feedback we receive from residents and businesses.

There will be a video presentation played at the start of the meeting. The presentation will also be posted online at https://www.cambridgema.gov/Departments/publicworks/cityprojects/2019/elmstreconstructionproject beginning Friday, December 11th, so that residents who wish to submit questions in advance of the meeting may do so. Advance questions, as well as new questions received “live”, will be answered during the meeting.

Information and Assistance

The City of Cambridge does not discriminate on the basis of disability. The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request. To receive future updates via email, please contact Kate Riley, Community Relations Manager, at kriley@cambridgema.gov / 617-349-4870.


Notice: Chapter 90, Contract 24 - Community Meeting Wednesday March 18th

Elm St., between Webster Ave. and Hampshire St., is scheduled for upcoming street and sidewalk reconstruction as part of the City’s 5 Year Plan.

The Department of Public Works and the City’s Community Development Department will be hosting a second community meeting on Wednesday, March 18th from 6PM-7:30PM at the Public Works Main Conference Room, 147 Hampshire Street to discuss the Elm St. Reconstruction Project.

City staff would like to discuss preliminary designs for traffic calming and safety improvements for the street. These designs were developed after receiving feedback at the first community meeting held Tuesday, October 15th, 2019. We encourage you to attend, as we value the feedback we receive from Cambridge residents and businesses.

Information and Assistance:


The City of Cambridge does not discriminate on the basis of disability. The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request. To receive future updates via email, please contact Kate Riley, Communications Manager at kriley@cambridgema.gov / 617.349.4870. For information about the project please contact Melissa Miguel, Supervising Engineer at mmiguel@cambridgema.gov. For traffic calming information contact Juan P. Avendano, Community Development Project Manager, at 617.349.4655 / javendano@cambridgema.gov.


Notice: Chapter 90, Contract 24 - Catch Basin Inspections

 

As part of the continued design process, crews will be inspecting catch basins beginning Tuesday 11/12. "No Parking" signs will be posted 48 hours in advance. Work will last approximately 1-2 days at each location.


Notice: Chapter 90, Contract 24 - Community Meeting Tuesday October 15th

Elm St., between Webster Ave. and Hampshire St., is scheduled for upcoming street and sidewalk reconstruction as part of the City’s 5 Year Plan.

The Department of Public Works will be hosting a community meeting on Tuesday, October 15th from 6PM-7:30PM at DPW offices located at 147 Hampshire Street to discuss the Elm St. Reconstruction Project.

The project is part of the City’s Complete Streets initiative to design and operate streets that are safe for all users including pedestrians, cyclists, motorists and public transit users. The focus of this meeting will be to discuss the design and construction process and solicit feedback from the community. We encourage you to attend, as we value the feedback we receive from Cambridge residents and businesses.

Information and Assistance:

The City of Cambridge does not discriminate on the basis of disability.   The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request.  For more information, please contact Melissa Miguel, Supervising Engineer, at 617-349-9351/ mmiguel@cambridgema.gov. To receive future updates via email, please contact Kate Riley, Community Relations Manager, at kriley@cambridgema.gov / 617-349-4870. 

 

Updated estimated schedule as of September 2024 (weather permitting):

Fall 2024:
Elm St (Hampshire St to Cambridge St) - Water work, full depth/binder roadway reconstruction, curb and sidewalk work

Elm St (Cambridge St to Webster Ave) – Water work, Full depth/binder roadway reconstruction

Fall 2024/Spring 2025:
Elm Street (Hampshire St to Cambridge St)- mill/final paving, pavement markings, punch list items

Spring 2025
Elm St (Cambridge St to Webster Ave) Curb and sidewalk work, mill/final paving, pavement markings, punch list items and project completion


Fall 2022: Project will go out to bid late summer.

Spring 2023: Construction to start.

This street is part of a larger package with several streets. The contract will start Fall 2020 but finite schedules are not determined until a contractor is on board. 


Fall 2019: This project is currently in the design phase.

Melissa Miguel - Supervising Engineer

mmiguel@cambridgema.gov

617-349-9351

 

Kristen Kelleher - Community Relations Manager

kkelleher@cambridgema.gov

617-349-4825

 

Sign Up Now

Page was posted on 10/1/2019 4:24 PM
Page was last modified on 12/10/2024 3:16 PM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.