As part of the Trenchless Rehabilitation Program for sewer and stormwater infrastructure, the city’s contractor, Insituform, will be rehabilitating the sewer mains using a method known as cast-in-place pipe (CIPP) lining. This system will provide a new structurally sound sewer pipe that will significantly reduce root and water infiltration problems and improve flow. This CIPP lining work does not require excavation; however, trucks and equipment will be onsite to complete the work. No Parking signs will be posted at least 24 hours in advance. Please check daily for No Parking signs. Police officers will be on site to assist with vehicle and cycling traffic and pedestrians.
Work hours are 7am until completion of work which is up to 10 hours each day. There will be a temporary disruption of sewer service to your residence or business during this time. Affected properties will receive two hand delivered notices. The first notice will be distributed several days in advance, and the second will be a 24-hour notice. It is very important to limit water use on the day specified in the notice.
Below is the schedule for March 21 to March 25, weather permitting:
- Tuesday March 22: Second Ave from Gore Street to Cambridge Street
- Wednesday March 23: Second Street from Thorndike Street to Cambridge Street (11am start)
- Thursday March 24: Second Street from Thorndike Street to Charles Street
- Friday March 25: Griswold Street from 71-73/74 Griswold Street to Loomis Street RESCHEDULED DUE TO SNOW
Contact information:
- Insituform Site Superintendent - Henry Boissonneault, 774-200-8404
- Insituform Project Engineer - Tom Bronczyk, 508-277-1030
- Department of Public Works Field Inspector, Lou Mothon, 617-349-4828